“Modernization of branches in order to reduce CPT by installing FDCP in Rm. Vâlcea, Vâlcea county”

Installation of FDCP 15 subscribers 27 pieces, FDCP 20 subscribers 22 pieces and BMPM 32A 39 pieces on block scale was executed. FDCP power supply through LES ACYY 4X70+MYF 25 in length 407m and LES ACYY 4X50 in length 517m, realization of earth sockets 7 pieces, installation of connection boxes 12 pieces, replacement of subscriber columns with CYY-F 3×6 mmp cable: 16145 m, mounted in a PVC cable channel; replacing the General Groove. After the completion of the assembly work, the meters were relocated in the new installations: 884 single-phase, 1 three-phase.

Work durationThe project was carried out between 30.08.2021-05.12.2021 (100 calendar days).

The work was completed with the introduction into the GIS of the TOPO coordinates and the plates of the construction elements for which this is necessary on 17.12.2021.

Team: We worked with 8 teams made up of 4 measurement-maintenance electricians, each team made one block ladder per week.

The team was equipped with electric hand tools: pickhammer, rotary hammer, angle grinder, cordless drill, portable lamps, ladders, extension cables.

Obstacles encountered: The degree of complexity of the work was of medium level, the biggest problems occurred when obtaining the consents of the Owners’ Associations prior to the execution.

Completion of work: 17.12.2021

Benefits for the customer: reduction of CPT, increased security of supply to consumers. The accessibility of measurement groups brings advantages for the distributor and the consumer, so that all interventions are made faster and easier.

 