MODERNISATION OF THE 110/20KV SUBSTATION – Adrem

MODERNISATION OF THE 110/20KV SUBSTATION

Energetic

VIDELE, TELEORMAN, FOR CEZ DISTRIBUTIE SA

 

FIELD:
Energy Industry

 

DESCRIPTION:
Engineering and execution of the engineering, procurement and construction plan (EPC)

Scope of the contract: automation and modernisation of the 110/20kV substation and rehabilitation of the existing equipment.

The project included full replacement of the high voltage equipment, the rehabilitation of two high and medium voltage transformers, of the ventilation system and of the auxiliary equipment and execution of civil works.

All primary and secondary circuits were modernised, through the replacement of medium and high voltage equipment and the new equipment was integrated in CEZ Distributie’s SCADA system and the existing construction was rehabilitated.

Poze proiect