Installation of photovoltaic panels for individuals – Adrem

Installation of photovoltaic panels for individuals

Renewable Energy

Clients: individuals and legal entities, beneficiaries through the Green House program or upon request

Installed power: 3kw / 5kw

Installation duration: 4h – 10h depending on location and conditions

Adrem Link team: 3 people

Equipment: solar panels (eg 12 panels for 3kw), smart meter, cables, other accessories

Description: Inspecting the location, determining the best way to place the solar panels so as to ensure maximum light and heat, establishing cable routes. This is followed by the preparation of the roof, the dismantling of any constructions on the roof (eg snow guards), the lifting of the panels and their fixing on the roof. After mounting the panels, they are connected to the panel and put into operation.