Clients: individuals and legal entities, beneficiaries through the Green House program or upon request
Installed power: 3kw / 5kw
Installation duration: 4h – 10h depending on location and conditions
Adrem Link team: 3 people
Equipment: solar panels (eg 12 panels for 3kw), smart meter, cables, other accessories
Description: Inspecting the location, determining the best way to place the solar panels so as to ensure maximum light and heat, establishing cable routes. This is followed by the preparation of the roof, the dismantling of any constructions on the roof (eg snow guards), the lifting of the panels and their fixing on the roof. After mounting the panels, they are connected to the panel and put into operation.