Engineering and execution of the engineering, procurement and construction plan (EPC)

The scope of the contract was the automation and modernisation of the substation, and the rehabilitation of existing equipment

Following the implementation of the project, all primary and secondary circuits were modernised, through the replacement of the medium and high voltage equipment and integration of the new equipment in CEZ DISTRIBUTIE’s SCADA system